Fives sets a new record for the manufacture of a cold box

20200922-BF 810 1901 Hyundai v2-FIVES

Once again, Fives teams in Golbey, France, proved that they could successfully rise to complex challenges and ensure that their client would receive their equipment on time.

20200922 BF Hyundai Aramco-FIVES

In only 3 months, the Energy | Cryogenics teams built a cold box for a gas plant in Saudi Arabia for Hyundai Engineering & Construction Co., Ltd, an impressive record time!

Indeed, it usually takes 6 to 8 months to design and manufacture similar cold boxes.

Weighing 52 tons and composed of 3 brazed aluminum heat exchangers (BAHX), the cold box could be built thanks to the skills, energy, and involvement of the teams, who had to, on top of a tight schedule, also work while complying with safety protocols in a time of Covid-19 and distancing rules.

Fives is proud of its Energy | Cryogenics teams’ great achievement as well as their commitment to go the extra mile to answer their client's needs.